UG Tasks Port Coquitlam

Client: BC Hydro & Power Authority

Location: Port Coquitlam, BC

Completion Date: March 31, 2016

Scope/Description:

  • Feeder dip isolations to allow for dead-end assembly upgrades.
  • Disconnect replacements
  • URD cable removed and replaced with new elbows with the corrected voltage rating.
  • Grounding fixes in junction boxes

Highlight(s):

  • 100+ tasks to complete to pre-underground checklist for conversion to 25kV including LPT and PMT changes, and JB remediations.